Official New Hampshire government website Official New Hampshire government website
IR 25-031
Electric Distribution Utilities
Investigation Into Distributed Generation in New Hampshire
TAB DATE DESCRIPTION FILED BY
1 04/16/2025 Order of Notice NHPUC
 
2 04/17/2025 Liberty Utilities (Granite State Electric) Corp. d/b/a Liberty Notice of Appearance and Request for Service List Change Jacob Roberts
 
3 04/24/2025 New Hampshire Department of Energy Notice of Appearance and Request for Service List Change Alexandra K. Ladwig, Amanda R. Zhang and Paul B. Dexter
 
4 04/25/2025 Granite State Hydropower Association Notice of Appearance Madeline Mineau
 
5 04/28/2025 Eversource Energy Notice of Appearance and Request for Service List Change David K. Wiesner
 
6 04/28/2025 Conservation Law Foundation Notice of Appearance and Request for Service List Change Nick Krakoff
Cover Letter
Notice of Appearance
 
7 04/28/2025 OCA Notice of Appearance and Request for Service List Change Donald M. Kreis
Cover Letter
Notice of Appearance
 
8 04/29/2025 Unitil Energy Systems, Inc. Notice of Appearance Patrick H. Taylor and Brody J. Haverly-Johndro
Cover Letter
Notice of Appearance
 
9 05/01/2025 Clean Energy New Hampshire Notice of Appearance Chris Skoglund
Cover Letter
Notice of Appearance
 
10 05/01/2025 Kearsarge Solar LLC Request for Remote Participation Samuel Feigenbaum
 
11 05/01/2025 Kearsarge Solar LLC Notice of Appearance and Request for Service List Change Samuel Feigenbaum
Cover Letter
Notice of Appearance
 
12 05/01/2025 Liberty Utilities (Granite State Electric) Corp. d/b/a Liberty Assented-to Motion for Remote Participation Michael J. Sheehan
Cover Letter
Motion
 
13 05/02/2025 Community Power Coalition of New Hampshire Notice of Appearance Clifton Below and Deana Dennis
 
14 05/02/2025 ReVision Energy Inc. Notice of Appearance and Request for Service List Change Stephen F Hinchman
Cover Letter
Notice of Appearance
 
15 05/02/2025 Procedural Order Re: Request for Remote Participation Filed by Liberty Utilities NHPUC
 
16 05/02/2025 Procedural Order Re: Request for Remote Participation Filed by Kearsarge Solar LLP NHPUC
 
17 05/16/2025 Procedural Order Re: Scoping Document NHPUC
Draft Commission Scoping Document
 
18 05/21/2025 Transcript of hearing held 05/05/25 eScribers
 
19 05/28/2025 Liberty Utilities (Granite State Electric) Corp. d/b/a Liberty 2024 Registered Group Host Facilities Report Tyler Culbertson
Cover Letter
Report
Confidential Material in Commission File
 
20 06/06/2025 Procedural Order Re: Annual Reports of Registered Group Host Facilities NHPUC
 
21 06/09/2025 Eversource Energy 2024 Annual Group Net Metering Report David K. Wiesner
Cover Letter
Report
Confidential Material in Commission File
 
22 06/11/2025 Joint Participants’ Comments in Response to May 16, 2025 scoping document Nick Krakoff, Sam Evans-Brown, Samuel Feigenbaum and Stephen Hinchman
 
23 06/11/2025 Eversource Energy Initial Response to Draft Scoping Document David K. Wiesner
 
24 06/11/2025 New Hampshire Department of Energy Comments on Draft Commission Scoping Document Alexandra K. Ladwig, Amanda R. Zhang and Paul B. Dexter
Cover Letter
Comments
 
25 06/11/2025 Community Power Coalition of New Hampshire Draft Comments on Scoping Document Clifton Below
Cover Letter
Comments
 
26 06/18/2025 New Hampshire EDC’s Reply Comments Regarding Scoping Document David K. Wiesner
 
27 06/19/2025 Community Power Coalition of New Hampshire Reply Comments Regarding Scoping Document Clifton Below
 

Exhibits


Comments

PUB. DATE FILED BY