Official New Hampshire government website Official New Hampshire government website
DG 12-242
Concord Steam Corporation
Notice of Intent to File Rate Schedules - CLOSED
TAB DATE DESCRIPTION FILED BY
1 07/30/2012 Notice of Intent to File Rate Schedules Peter Bloomfield
 
2 08/02/2012 Sec Ltr Acknowledgement Debra A. Howland
 
3 09/05/2012 CSC Rate Schedules Peter Bloomfield
Direct Testimony of P Bloomfield-Permanent
Cover Letter-TOC
Petition for Temporary Rates
Tariff pages
Direct Testimony of P Bloomfield-Temporary
Attachments for Permanent and Temporary
Puc Rule 1604.01
*Marked as Exhibit 1 at 10/23/12 hearing
 
4 09/14/2012 Order No. 25,410 Suspending Proposed Tariff and Scheduling Prehearing Conference and Temporary Rate Hearing NHPUC
 
5 10/19/2012 CSC Settlement Agreement – Temporary Rates Patrick H. Taylor
Cover Letter
Agreement
Marked as Exhibit 2 at 10/23/12 hearing
 
6 10/19/2012 Staff Pre-filed Testimony of Stephen P. Frink Staff
Cover Letter
Testimony
Attachments
*Marked as Exhibit 4 at 10/23/12 hearing
 
7 10/23/2012 CSC Affidavit of Publication Cathy A. Valley
 
8 10/23/2012 Clerks Report Staff
*Exhibit 1 see Tab 3
*Exhibit 2 see Tab 5
Exhibit 3
*Exhibit 4 see Tab 6
 
9 10/30/2012 Order No. 25,432 On Petition for Temporary Rates and Addressing Waiver Requests NHPUC
 
10 11/02/2012 CSC revised tariff page Peter Bloomfield
Cover Letter
Tariff Pg
*Tariff pg 59th pg 11
 
11 11/06/2012 Transcript of hearing held October 23,2012 Steven E. Patnaude
Condensed version in Commission File not Scanned
 
12 11/05/2012 CSC submitting corrected revised tariff page Peter Bloomfield
Cover Letter
Tariff pg
*Tariff pg57th rev pg 11
 
13 11/08/2012 Staff Ltr of Compliance Staff
*Tariff pg57th rev pg 11
 
14 11/27/2012 Staff ltr proposed procedural schedule Staff
 
15 11/29/2012 Sec Ltr Approving Procedural Schedule Debra A. Howland
 
16 03/15/2013 Staff Testimony of Stephen P. Frink Staff
Cover Letter
Testimony
Attachments
*Marked as Exhibit 5 at 04/03/13 hearing
 
17 03/18/2013 Staff-CSC Settlement Agreement Staff
Cover Letter
Agreement
 
18 03/20/2013 Staff Resubmission of Settlement Agreement to correct clerical errors Staff
Cover Letter
Resubmitted Agreement
*Marked as Exhibit 6 at 04/03/13 hearing
 
19 03/20/2013 Sec Ltr Scheduling of Hearing Debra A. Howland
 
20 03/28/2013 CSC Motion for Protective Order and Confidential Treatment of certain Discovery Patrick H. Taylor
Cover Letter
Motion
 
21 03/29/2013 McLane Law Firm Withdrawal of Appearance including but not limited to Patrick H. Taylor and Steven V. Camerino Patrick H. Taylor
 
22 04/03/2013 Clerk’s Report Staff
*Exhibit 5 see Tab 16
*Exhibit 6 see Tab 18
Exhibit 7
Exhibit 8
 
23 04/15/2013 Transcript of hearing held on 04-03-13 Steven E. Patnaude
 
24 04/25/2013 Order No. 25,499 Approving Permanent Rates NHPUC
Case Closed
 
25 04/30/2013 CSC Tariff page revisions Peter Bloomfield
Cover Letter
Tariff pgs
*Tariff pg 58th rev pg 11 and 3rd rev pg 12
 
26 05/06/2013 Staff Ltr of Compliance Staff
*58th rev pg 11 and 3rd rev pg 12
 
27 11/08/2013 Concord Steam Corp Tariff Peter Bloomfield
Cover Letter
Tariff
*Tariff Supp #7 original pg 1
 
28 11/14/2013 Staff Ltr or compliance Staff
*Tariff Supp #7 original pg 1
 

Exhibits

DATE NO. DESCRIPTION

10/23/2012 1 CSC Rate Schedules Peter Bloomfield
Cover Letter-TOC
Petition for Temporary Rates
Tariff pages
Direct Testimony of P Bloomfield-Permanent
Direct Testimony of P Bloomfield-Temporary
Attachments for Permanent and Temporary
Puc Rule 1604.01
*Filed 09/05/12 Tab 3 of original filing

10/23/2012 2 CSC Settlement Agreement – Temporary Rates Peter Bloomfield
Cover Letter
Agreement
*Filed 09/19/12 Tab 5 of original filing

10/23/2012 3 CSC Revised Schedule A of the Settlement Agreement

10/23/2012 4 Staff Pre-filed Testimony of Stephen P. Frink Stephen P. Frink
Cover Letter
Testimony
Attachments
*Filed 09/19/12 Tab 6 of original filing

04/03/2013 5 Staff Testimony of Stephen P. Frink Peter Bloomfield and Stephen P. Frink
Cover Letter
Testimony
Attachments
*Filed 03/15/13 Tab 16 of original filing

04/03/2013 6 Staff Resubmission of Settlement Agreement to correct clerical errors Peter Bloomfield and Stephen P. Frink
Cover Letter
Resubmitted Agreement
*Filed 03/20/13 Tab 18 of original filing

04/03/2013 7 Staff Audit Report

04/03/2013 8 Concord Monitor Article- Still without financing, Concord Steam makes backup plan to stay put

Comments

PUB. DATE FILED BY