Home

DE 23-009

Squam River Hydro, LLC

Petition for Reconnection of a Qualifying Facility, Payment of Avoided Cost, and Payment of Lost Revenues

TAB

DATE

DESCRIPTION

FILED BY

1

01/31/23

Petition for Reconnection of a Qualifying Facility, Payment of Avoided Cost, and Payment of Lost Revenues

Cover Letter
Petition
Notice of Appearance of Douglas L. Patch

Douglas L. Patch

2

02/01/23

Acknowledgment Letter

NHPUC

3

02/10/23

New Hampshire Department of Energy Notice of Appearance

Suzanne G. Amidon

4

02/23/23

Town of Ashland Notice of Appearance and Request for Service List Change

Thomas B. Getz and Viggo C. Fish

5

03/31/23

Commencement of Adjudicative Proceeding and Notice of Prehearing Conference

NHPUC

6

03/31/23

Hearing Guidelines

NHPUC

7

04/11/23

Squam River Hydro, LLC Affidavit of Publication

Douglas L. Patch

8

05/02/23

Town of Ashland's Preliminary Response to Petition of Squam River Hydro, LLC

Cover Letter
Response

Thomas B. Getz

9

05/10/23

Procedural Order Re: Briefing Schedule

NHPUC

10

05/17/23

Squam River Hydro, LLC Proposed Procedural Schedule

Thomas B. Getz

11

05/18/23

Procedural Order Re: Proposed Briefing Schedule

NHPUC

12

06/16/23

Town of Ashland Initial Brief on Jurisdiction

Cover Letter
Brief
Attachments

Thomas B. Getz

13

06/16/23

Squam River Hydro, LLC Brief Regarding Jurisdiction of NHPUC

Cover Letter
Brief
Attachments

Douglas L. Patch

14

06/30/23

Squam River Hydro, LLC Reply Brief

Cover Letter
Reply Brief

Douglas L. Patch

15

06/30/23

Town of Ashland Reply Brief on Jurisdiction

Cover Letter
Reply Brief

Thomas B. Getz

16

09/22/23

Procedural Order Re: Oral Argument

NHPUC

17

10/12/23

New Hampshire Department of Energy Position Statement

Suzanne G. Amidon

18

11/07/23

Clerk Report

NHPUC

19

11/07/23

Procedural Order Re: Supplemental Filings

NHPUC

20

11/17/23

Squam River Hydro, LLC Response to NHPUC Order of 11/07/23 Requesting Additional Information

Cover Letter
Response
Attachment

Douglas L. Patch

21

11/17/23

New Hampshire Department of Energy Position Statement

Suzanne G. Amidon

22

11/17/23

Town of Ashland Response to NHPUC Order of 11/07/23

Response
Attachment

Viggo C. Fish

23

11/28/23

Transcript of Hearing Held 11/07/23

Steven E. Patnaude

24

11/30/23

Squam River Hydro, LLC Response to Town of Ashland and New Hampshire Department of Energy Submissions

Cover Letter
Response

Douglas L. Patch

25

01/25/24

Order No. 26,937 Order Regarding Jurisdiction

NHPUC

26

02/23/24

Squam River Hydro, LLC Motion for Rehearing of Order No. 26,937

Cover Letter
Motion
Attachments

Douglas L. Patch

 

 


EXHIBITS


DATE

NO.

DESCRIPTION

WITNESS