DE 16-823

Eversource Energy

Petition for Adjustment to Stranded Cost Recovery Charge

Click here to go to Exhibits Page

TAB

DATE

DESCRIPTION

FILED BY

1

09/30/16

Petition for Adjustment to Stranded Cost Recovery Charge for effect on January 1, 2017

Cover Letter
Petition
Testimony of David F. Bidmead
Attachments-D. Bidmead

Marked as Exhibit 1 at 12/15/16 hearing

Matthew J. Fossum

2

10/04/16

Sec Ltr Acknowledgement

Debra A. Howland

3

10/10/16

OCA Ltr of Participation

Donald M. Kreis

4

10/10/16

Order of Notice

Debra A. Howland

5

10/19/16

Eversource Energy Affidavit of Publication

Matthew J. Fossum

6

10/27/16

Clerk Report

Prehearing conference

Staff

7

10/31/16

Staff Report of Technical Session and Proposed Procedural Schedule

Staff

8

11/09/16

Transcript of hearing held on 10/27/16

Steven E. Patnaude

9

11/28/16

Sec Ltr approving procedural schedule

Debra A. Howland

10

12/09/16

Eversource Energy Technical Statement and updated exhibits of David F. Bidmead

Cover Letter
Technical Statement
Attachments

Marked as Exhibit 2 at 12/15/16 hearing

Matthew J. Fossum

11

12/14/16

Eversource Energy Corrected Exhibit DFB-3, Pg 4 of 4 of David F. Bidmead

Cover Letter
Corrected Exhibit

Marked as Exhibit 3 at 12/15/16 hearing

Matthew J. Fossum

12

12/15/16

Clerk Report

Staff

13

12/23/16

Order No. 25,975 Approving Stranded Cost Recovery Charge

NHPUC

14

12/29/16

Transcript of hearing held on 12/15/16

Steven E. Patnaude

15

01/05/17

Eversource Energy Compliance Tariff NHPUC No. 9

Cover Letter
Tariff pages
Attachments

1st rev pg 22, 2nd rev pgs 19, 41-42, 45-47, 50-52, 55, 59, 62, 66-67, 72, 74, 81, and 90

Lois B. Jones

16

05/09/17

Eversource Energy Preliminary Mid-Year Adjustment with Prefiled Testimony and Technical Statement of David F. Bidmead

Cover Letter
Testimony D. Bidmead
Tech Statement D. Bidmead
Attachment D. Bidmead

Marked as Exhibit 5 at 06/22/16 hearing

Matthew J. Fossum

17

05/15/17

Eversource Energy 2017 Qtr 1 Stranded Cost Recovery Charge Rate reconciliation report

Matthew J. Fossum

18

05/18/17

Order of Notice

Debra A. Howland

19

05/24/17

Eversource Energy Affidavit of Publication

Matthew J. Fossum

20

06/16/17

Eversource Energy Mid-Year Adjustment Update with Technical Statement of David F. Bidmead

Cover Letter
Technical Statement of Bidmead
Updated Attachments-Bidmead

Marked as Exhibit 6 at 06/22/16 hearing

Matthew J. Fossum

21

06/22/17

Clerk Report

Staff

22

06/28/17

Order No. 26,032 Approving Adjustment to Stranded Cost Recovery Charge Rate

NHPUC

23

07/07/10

Eversource Energy Compliance Tariff NHPUC No. 9

Cover Letter
Tariff pages
Comparison of Rates
Summary of Rates
Typical Bill Comparisons
2nd rev pgs 58, 60, 61, 64, 68, 71, 75, 76, 82, 83 and 3rd rev pgs 19, 41, 42, 45, 46, 47, 50, 51, 52, 55, 59, 62, 66, 67, 72, 74, 81 and 90

Lois B. Jones

24

07/13/17

Transcript of hearing held on 6/22/17

Steven E. Patnaude

25

07/20/17

Staff Ltr of Compliance

2nd rev pgs 58, 60, 61, 64, 68, 71, 75, 76, 82, 83 and 3rd rev pgs 19, 41, 42, 45, 46, 47, 50, 51, 52, 55, 59, 62, 66, 67, 72, 74, 81 and 90

Staff

26

08/15/17

Eversource Energy 2017 Qtr 2 Stranded Cost Recovery Charge and Energy Service Rate reconciliation report

Matthew J. Fossum

27

11/15/17

Eversource Energy 2017 Qtr 3 Stranded Cost Recovery Charge and Energy Service Rate reconciliation report

Matthew J. Fossum

28

02/26/18

Eversource Energy 2017 Qtr 4 Stranded Cost Recovery Charge and Energy Service Rate reconciliation report

Matthew J. Fossum

 

 


EXHIBITS


DATE

NO.

DESCRIPTION

WITNESS

12/15/16

1

Petition for Adjustment to Stranded Cost Recovery Charge for effect on January 1, 2017

Filed 09/30/16 Tab 1 of the docket

12/15/16

2

Eversource Energy Technical Statement and updated exhibits of David F. Bidmead

Filed 12/09/16 Tab 10 of the docket

12/15/16

3

Eversource Energy Corrected Exhibit DFB-3, Pg 4 of 4 of David F. Bidmead

Filed 12/14/16 Tab 11 of the docket

12/15/16

4

Eversource Energy Comparison of Current and Proposed Residential Rate R And Calculation of a 625 kWh Monthly Bill by Rate Component

06/22/17

5

Eversource Energy Preliminary Mid-Year Adjustment

Filed 05/09/17 Tab 16 of the docket

06/22/17

6

Eversource Energy Mid-Year Adjustment Update

Filed 06/16/17 Tab 20 of the docket

06/22/17

7

Eversource Energy Comparison of Current and Proposed Residential Rate R And Calculation of a 600 kWh Monthly Bill by Rate Component JuIy l, 2017

Witness: David F. Bidmead

 

 

An Official Web Site for New Hampshire Government