DR 98-016
Public Service Company of New Hampshire
Petition For Approval of Financing
Order Approving Procedural Schedule
O R D E R N O. 22,872
March 16, 1998
On February 20, 1998, Public Service Company of New
Hampshire (PSNH) filed with the New Hampshire Public Utilities
Commission (Commission) a Petition for Approval of Extension,
Modification and/or Amendment of Various Finance Arrangements,
for Issuance of First Mortgage Bonds and for the Granting of
Additional Security, together with accompanying attachments.
By Order of Notice issued February 23, 1998, the
Commission scheduled a prehearing conference for March 5, 1998,
set deadlines for intervention requests and objections thereto,
outlined a proposed procedural schedule, and required the Parties
and the Commission Staff (Staff) to summarize their positions
with regard to the filing for the record.
Cabletron Systems, Inc. (Cabletron) moved to intervene
by written motion stating the basis of its interest in the
proceeding. At the prehearing conference, we granted Cabletron's
motion to intervene. The Office of the Consumer Advocate (OCA)
is a statutorily recognized intervenor and did appear at the
prehearing conference on March 5, 1998.
At the prehearing conference the Parties and Staff
agreed to the procedural schedule as outlined in the Order of
Notice and as follows:
Written Data Requests by Staff and
Intervenors March 6 , 1998
Company Data Responses March 9, 1998
Testimony by Staff and
Intervenors March 13, 1998
Hearing on the Merits March 17, 1998 at 1:30 p.m.
March 18, 1998 at 10:00 a.m.
Commission Written Order March 20, 1998
Motions for Rehearing, if any April 20, 1998
Commission Decision on Motions for
Rehearing, if any April 22, 1998;
Also at the prehearing conference, in accordance with
the Order of Notice, PSNH and Staff stated their positions with
regard to the filing for the record.
We find the proposed procedural schedule to be
reasonable and will, therefore, approve it for the duration of
the proceeding.
Based upon the foregoing, it is hereby
ORDERED, that the procedural schedule delineated above
is APPROVED; and it is
FURTHER ORDERED, that Cabletron Systems, Inc is granted
intervenor status.
By order of the Public Utilities Commission of New
Hampshire this sixteenth day of March, 1998.
Douglas L. Patch Bruce B. Ellsworth Susan S. Geiger
Chairman Commissioner Commissioner
Attested by:
Thomas B. Getz
Executive Director and Secretary