DR 97-195
Concord Electric Company
and
EXETER & HAMPTON ELECTRIC COMPANY
PETITION TO RECOVER ADMINISTRATIVE COSTS
ASSOCIATED WITH THE PILOT PROGRAM
Order Scheduling Hearing
O R D E R N O. 22,834 January 12, 1998
APPEARANCES: Susan L. Geiser, Esq. for Concord Electric
Company and Exeter & Hampton Electric Company; and Robert J.
Frank for the Staff of the New Hampshire Public Utilities
Commission.
I. PROCEDURAL HISTORY
On September 22, 1997, Concord Electric Company and
Exeter & Hampton Electric Company (Unitil Companies or Unitil)
filed with the Commission a Petition to Recover Administrative
Costs Associated with the Pilot Program.
By Order No. 22,795 issued December 1, 1997, the
Commission initiated an investigation regarding recovery,
suspended the proposed tariff pages pending further review and
decision, scheduled a prehearing conference for January 5, 1998,
set deadlines for intervention requests and objections thereto,
and required the Parties and Commission Staff (Staff) to
summarize their positions with regard to the filing for the
record. No party moved to intervene.
At the prehearing conference, the Unitil Companies and
Staff proposed a hearing date of January 20, 1998 at 10:00 a.m.
In accordance with the Order of Notice, the Unitil
Companies and Staff stated their positions with regard to the
filing for the record.
Unitil stated that it had voluntarily declined to start
collecting the petitioned for expenses prior to the suspension
order and that the Companies had worked with the Commission audit
staff regarding outstanding issues.
Staff stated that discussions with Unitil had allayed
many of the original concerns of the Staff regarding the proposed
recovery and that two key issues remained, namely (1) how the
pilot program expenses were kept on the Unitil books, and (2) the
proposed timing of the recovery of the expenses by Unitil.
II. COMMISSION ANALYSIS
Unitil and Staff have proposed scheduling a hearing at
which Unitil will present its proposal for recovery or a
settlement agreement, if arrived at with Staff. We find that
proposal reasonable and will schedule a hearing.
Based upon the foregoing, it is hereby
ORDERED, that a hearing is scheduled in this matter for
January 20, 1998 at 10:00 a.m. at the Commission.
By order of the Public Utilities Commission of New
Hampshire this twelfth day of January, 1998.
Douglas L. Patch Bruce B. Ellsworth Susan S. Geiger
Chairman Commissioner Commissioner
Attested by:
Thomas B. Getz
Executive Director and Secretary