DG 12-242

Concord Steam Corp.

Notice of Intent to File Rate Schedules

Click here to go to Exhibits Page

TAB

DATE

DESCRIPTION

FILED BY

  •  

07/30/12

Notice of Intent to File Rate Schedules

Peter Bloomfield

  •  

08/02/12

Sec Ltr Acknowledgement

Debra A. Howland

  •  

09/05/12

CSC Rate Schedules

Cover Letter-TOC
Petition for Temporary Rates
Tariff pages
Direct Testimony of P Bloomfield-Permanent
Direct Testimony of P Bloomfield-Temporary
Attachments for Permanent and Temporary
Puc Rule 1604.01

Marked as Exhibit 1 at 10/23/12 hearing

Peter Bloomfield

  •  

09/14/12

Order No. 25,410 Suspending Proposed Tariff and Scheduling Prehearing Conference and Temporary Rate Hearing

NHPUC

  •  

10/19/12

CSC Settlement Agreement - Temporary Rates

Cover Letter
Agreement

Marked as Exhibit 2 at 10/23/12 hearing

Patrick H. Taylor

  •  

10/19/12

Staff Pre-filed Testimony of Stephen P. Frink

Cover Letter
Testimony
Attachments

Marked as Exhibit 4 at 10/23/12 hearing

Staff

  •  

10/23/12

CSC Affidavit of Publication

Cathy A. Valley

  •  

10/23/12

Clerks Report

Exhibit 1 see Tab 3

Exhibit 2 see Tab 5

Exhibit 3

Exhibit 4 see Tab 6

Staff

  •  

10/30/12

Order No. 25,432 On Petition for Temporary Rates and Addressing Waiver Requests

NHPUC

  •  

11/02/12

CSC revised tariff page

Cover Letter
Tariff Pg

Tariff pg 59th pg 11

Peter Bloomfield

  •  

11/06/12

Transcript of hearing held October 23,2012

Condensed version in Commission File not Scanned

Steven E. Patnaude

  •  

11/05/12

CSC submitting corrected revised tariff page

Cover Letter
Tariff pg

Tariff pg57th rev pg 11

Peter Bloomfield

  •  

11/08/12

Staff Ltr of Compliance

Tariff pg57th rev pg 11

Staff

  •  

11/27/12

Staff ltr proposed procedural schedule

Staff

  •  

11/29/12

Sec Ltr Approving Procedural Schedule

Debra A. Howland

  •  

03/15/13

Staff Testimony of Stephen P. Frink

Cover Letter
Testimony
Attachments

Marked as Exhibit 5 at 04/03/13 hearing

Staff

  •  

03/18/13

Staff-CSC Settlement Agreement

Cover Letter
Agreement

Staff

  •  

03/20/13

Staff Resubmission of Settlement Agreement to correct clerical errors

Cover Letter
Resubmitted Agreement

Marked as Exhibit 6 at 04/03/13 hearing

Staff

  •  

03/20/13

Sec Ltr Scheduling of Hearing

Debra A. Howland

  •  

03/28/13

CSC Motion for Protective Order and Confidential Treatment of certain Discovery

Cover Letter
Motion

Patrick H. Taylor

  •  

03/29/13

McLane Law Firm Withdrawal of Appearance including but not limited to Patrick H. Taylor and Steven V. Camerino

Patrick H. Taylor

  •  

04/03/13

Clerk's Report

Exhibit 5 see Tab 16

Exhibit 6 see Tab 18

Exhibit 7
Exhibit 8

Staff

  •  

04/15/13

Transcript of hearing held on 04-03-13

Steven E. Patnaude

  •  

04/25/13

Order No. 25,499 Approving Permanent Rates

NHPUC

  •  

04/30/13

CSC Tariff page revisions

Cover Letter
Tariff pgs

Tariff pg 58th rev pg 11 and 3rd rev pg 12

Peter Bloomfield

  •  

05/06/13

Staff Ltr of Compliance

58th rev pg 11 and 3rd rev pg 12

Staff

 

 


EXHIBITS


DATE

NO.

DESCRIPTION

WITNESS

10/23/12

1

CSC Rate Schedules

Filed 09/05/12 Tab 3 of original filing

Peter Bloomfield

10/23/12

2

CSC Settlement Agreement - Temporary Rates

Filed 09/19/12 Tab 5 of original filing

Peter Bloomfield

10/23/12

3

CSC Revised Schedule A of the Settlement Agreement

Peter Bloomfield

10/23/12

4

Staff Pre-filed Testimony of Stephen P. Frink

Filed 09/19/12 Tab 6 of original filing

Stephen P. Frink

04/03/13

5

Staff Testimony of Stephen P. Frink

Filed 03/15/13 Tab 16 of original filing

Peter Bloomfield and Stephen P. Frink

04/03/13

6

Staff Resubmission of Settlement Agreement to correct clerical errors

Filed 03/20/13 Tab 18 of original filing

Peter Bloomfield and Stephen P. Frink

04/03/13

7

Staff Audit Report

Peter Bloomfield and Stephen P. Frink

04/03/13

8

Concord Monitor Article- Still without financing, Concord Steam makes backup plan to stay put

Peter Bloomfield and Stephen P. Frink