DE 08-057
NEW HAMPSHIRE ELECTRIC COOPERATIVE
2008 LongRange Plans for Bulk Power Supply Facilities
TAB
DATE
DESCRIPTION
FILED BY
05/05/08
2008 Long Range Plans for Bulk Power Supply Facilities
Jay Hutchison
05/06/08
To Hutchison Standard Acknowledgement Letter
Debra A. Howland
07/31/08
Memo/Staff’s Recommendation
Staff
08/01/08
Sec Ltr seeks your input on whether further action is required- attached Proposed Public Notice
08/15/08
Department of Environmental Services request for extension of time to August 22, 2008
Roberts J. Benedict
08/21/08
Sec ltr time to respond has been extended to August 22, 2008
08/26/08
Department of Environmental Services Ltr Delegates to the PUC its Responsibilities for summarizing and making Public the Annual Updated Long Range Plans for the Bulk Power Supply Facilities.
Michael J. Walls
09/04/08
Public Notice
NHPUC
09/05/08
Please publish OON in Union Leader
Adele Leighton
09/18/08
Affidavit of Publication
Phyllis Gilbert